Lane closures begin on the Talmadge Bridge for survey work ahead of cable replacement

GDOT contractors will run intermittent single-lane closures on the Talmadge Memorial Bridge on weekdays from Sept. 10 to 25 to survey the span before replacing its cables.

Gallery1 / 2

Talmadge Bridge
Project imageTalmadge BridgeCushman & Wakefield | Gilbert & Ezelle
Freighter Talmadge Bridge
Project contextFreighter Talmadge BridgeCushman & Wakefield | Gilbert & Ezelle

Georgia DOT crews will close one lane at a time on the Talmadge Memorial Bridge over the Savannah River, weekdays from Sept. 10 to 25 between 7 a.m. and 4 p.m., with at least one lane open in each direction.

The work lets crews survey and inspect the bridge ahead of a cable replacement expected to begin later this year, part of a larger maintenance job that also covers bearings and joints. GDOT is studying whether shortening the cables could raise the bridge's clearance, which the Georgia Ports Authority says would let larger container ships reach the Port of Savannah.

GDOT says the bridge is safe and the work is planning for the future.

What to watch

The start of cable replacement later in 2026 and GDOT's decision on whether shortening the cables will raise the bridge's clearance for larger ships.

JurisdictionCity of Savannah
ScaleSingle-lane, one-direction closures; cables, bearings and joints in the full project
TimelineClosures Sept 10-25, 2026, weekdays 7 a.m.-4 p.m.; cable replacement later in 2026
WhoGeorgia DOT; Georgia Ports Authority
Sources and documents3 sources

See an error, or have an update on this project? Tell Urban Savannah.

Connected coverage

Follow the thread

All updates

Explore the projects, places, developers and public systems connected to this story. Each card explains the link.