Savannah begins removing the MLK Jr. Civic Center arena, the first step toward housing on the site

The city kicked off a $10.9 million project to demolish the Dr. Martin Luther King Jr. Arena by hand, the opening move in a redevelopment that is set to bring 200-300 housing units and 45,000 square feet of retail to the 7-acre downtown site.

OPENING301 W. Oglethorpe Ave. (MLK Jr.Civic Center), Downtown SavannahAug 24, 2026

Savannah held a pre-demolition ceremony, "Honoring the Legacy, Building the Future," marking the start of the Civic Legacy - Arena Removal project at the Dr. Martin Luther King Jr. Civic Center. City Council approved a $10.9 million guaranteed maximum price for the work in early 2026.

Site prep and fencing began in March, and crews will hand-demolish the 1972 arena, no wrecking ball, no explosives, working within 30 feet of the wall by hand so the rest of the building isn't damaged. The job is expected to take about 13 months, with completion targeted for spring 2027.

Council set this in motion in June 2024, after EnMarket Arena opened downtown and took over as the city's main event venue. The Johnny Mercer Theatre, ballroom and meeting rooms stay open throughout construction. Once the arena footprint is clear, the city plans 200 to 300 housing units, 40 to 60 of them row homes, plus 45,000 square feet of local retail and a new municipal office building, with new hotel development on the site prohibited.

Mayor Van Johnson and city officials handed out bricks from the arena wall as keepsakes at the ceremony; one went to the city's Office of Municipal Archives & History for a future exhibit on the Civic Center's 50-plus years hosting concerts and conventions.

Why it matters

This is the first physical step in reclaiming 7 acres of downtown land for housing after 50 years as a single-use arena, and the city has already ruled out replacing it with another hotel.

JurisdictionCity of Savannah
Scale$10.9M arena removal; 7 acres; future 200-300 housing units, 45,000 sq ft retail
TimelineSite prep began March 2026; arena demolition ~13 months; complete spring 2027
WhoCity of Savannah
Sources and documents6 sources

See an error, or have an update on this project? Tell Urban Savannah.

Connected coverage

Follow the thread

All updates

Explore the projects, places, developers and public systems connected to this story. Each card explains the link.